When planning a PV installation, it is important to identify the nearest connection point to the grid to determine how the system will integrate with the existing infrastructure.

Obtaining Special Conditions Verification of the Possibility of Connecting a Household with its own Production requires: preparation and collection of documentation and completion of application for the issuance of electricity approval from HEP ODS

Предлага се от
HEP ODS
Какво трябва да предостави инициаторът

Document of legality of existing building; Document of ownership of building; Construction plans; Structural analysis; Electrical installation project for PV plant

Резултат

Special Conditions Verification obtained from HEP ODS; Offer for equipment for billing metering point from HEP ODS

Оставащи пречки

Insufficient capacity of the DSO in certain periods