AT: Analysis - Grid Connection Costs
English
Deutsch
Pay grid provision fee (Netzbereitstellung) and the grid access fee (Netzzutrittsentgelt). The distribution system operator has 2 weeks (network level 7) or 1 month (network levels 1 to 6) from the receipt of a request to provide a cost estimate.
Request cost estimate.
- Ce que le porteur de projet doit fournir
System Size (kW); Name, address, and contact information of the grid user; The specification of the Power rating of the grid connection point; The bottleneck capacity of the power generation system
- Résultat
Cost estimate
- Obstacles restants
Pay the fees