AT: Analysis - Max Feed-In Steiermark
English
Deutsch
For systems up to 250 kW, the feed-in capacity can be temporarily or generally reduced to an agreed maximum value to guarantee safe and efficient operation of the grid. The limitation may not exceed 1% of the maximum capacity at the grid connection point.
Find how much feed-in the grid can handle. If the grid infrastructure is limited, your feed-in power may be restricted.
- Proposé par
- Energy Netze Steiermark
- Ce que le porteur de projet doit fournir
Smart meter's ID (aka Measurement Point)
- Résultat
Max available feed in power
- Obstacles restants
Some regions only allow a small feed in power