BG 08-1: Analysis - Connection to the power grid for self consumption
English
български
Identify the nearest connection point to the grid with the DSO and check whether there are possibilities for augmentation of the feed in power. Check if there are any limitations on feed-in power, as well as the hardware requirements for connecting the PV system to the grid.
Explore with DSO the available on-site options for connecting the PV plant, energy storage and direct power lines for self consumption by CEP/EC participants.
- Proposé par
- Electricity System Operator Bulgaria (ESO)
- Ce que le porteur de projet doit fournir
Application for connection to the grid. Wiring schemes and drawings of existing building.
- Résultat
Wiring schemes (internal and external) for all buildings and direct power lines within the scope of the CEP/EC approved by the DSO.
- Obstacles restants
Not enough connection capacity to the grid infrastructure.