Assessment whether the existing power cabinets that service the building are sufficient to handle the current of the PV plant. Determine the ownership of power cabinets.

Determine the possible capacity of the PV installation with regard to the capacity of the existing power cabinets connecting to the grid.

Proposé par
Electricity System Operator Bulgaria (ESO)
Ce que le porteur de projet doit fournir

Application by the investor. Wiring schemes and drawings of existing building. Block diagram and single pole diagram of existing distribution cabinets.

Résultat

Block diagram and single pole diagrams of all required distribution cabinets.