To build a PV plant first of all is necessary to obtain preliminary permit by the DSO, stating that connection to the grid in the area is possible and is generally available.

Apply to the grid operator for feed-in power for the PV installation. For systems up to 30 kWp the grid operator is obliged to connect the PV plant to the grid.

Proposé par
Electricity System Operator Bulgaria (ESO)
Ce que le porteur de projet doit fournir

Existing grid connection points ID; Application to connect to the public power grid.

Résultat

Approval for connecting to the power grid in the form of operation contract and power-in permit.