Obtain information of the DSO free grid capacity to assess whether it will be possible to sell surplus energy to the electricity market.

Submit an application to the DSO in order to find the free capacity of the grid connection line and of the local transformer unit or substation.

Pruža
Electricity System Operator Bulgaria (ESO)
Što inicijator treba dostaviti

Building location; building drawings, investment concept, notary deed.

Rezultat

Detailed load diagrams and confirmation/approval by the DSO for sufficient free grid capacity.