BG 09-3: Obtaining a Permit for connection to the grid
English
български
To build a PV plant first of all is necessary to obtain preliminary permit by the DSO, stating that connection to the grid in the area is possible and is generally available.
Apply to the grid operator for feed-in power for the PV installation. For systems up to 30 kWp the grid operator is obliged to connect the PV plant to the grid.
- Pruža
- Electricity System Operator Bulgaria (ESO)
- Što inicijator treba dostaviti
Existing grid connection points ID; Application to connect to the public power grid.
- Rezultat
Approval for connecting to the power grid in the form of operation contract and power-in permit.