HR-09-Analysis - Power Grid
When planning a PV installation, it is important to identify the nearest connection point to the grid to determine how the system will integrate with the existing infrastructure.
Obtaining Special Conditions Verification of the Possibility of Connecting a Household with its own Production requires: preparation and collection of documentation and completion of application for the issuance of electricity approval from HEP ODS
- Pruža
- HEP ODS
- Što inicijator treba dostaviti
Document of legality of existing building; Document of ownership of building; Construction plans; Structural analysis; Electrical installation project for PV plant
- Rezultat
Special Conditions Verification obtained from HEP ODS; Offer for equipment for billing metering point from HEP ODS
- Preostale prepreke
Insufficient capacity of the DSO in certain periods