Pay grid provision fee (Netzbereitstellung) and the grid access fee (Netzzutrittsentgelt). The distribution system operator has 2 weeks (network level 7) or 1 month (network levels 1 to 6) from the receipt of a request to provide a cost estimate.

Request cost estimate.

Ce que le porteur de projet doit fournir

System Size (kW); Name, address, and contact information of the grid user; The specification of the Power rating of the grid connection point; The bottleneck capacity of the power generation system

Résultat

Cost estimate

Obstacles restants

Pay the fees