When planning a PV installation, it is important to identify the nearest connection point to the grid. Check if there are any limitations on feed-in power. Review the hardware requirements for connecting your PV system to the grid.

Support to request an approval from power grid operator for your PV plant. The fee for obtaining the estimate varies based on the system's power capacity.

Pruža
E-distribuzione
Što inicijator treba dostaviti

Sign up on the e-distribuzione website; Enter the location, general system data, and the required attachments, including the cadastral map, electrical diagram, and the fee.

Rezultat

After submitting the connection request, you will receive the corresponding quote. The timeframes prescribed by ARERA are: 20 working days for power up to 100 kW; 45 working days for up to 1,000 kW; 60 working days for over 1,000 kW.

Preostale prepreke

The grid operator can limit the feed-in