AT: Permit - Grid Connection
English
Deutsch
Grid operators cannot deny Systems <= 20 kW from being connected to the grid. A feed-in capacity is guaranteed up to the extent of the already agreed consumption capacity.
Request an approval from power grid operator for your PV plant.
- What the initiator needs to provide
Peak power production in kWp; Name and address; site plan; Desired start date for feed-in; Maximum capacity of the system in kW; Number and location of meter points; Type of system and operation
- Result
Grid access contract
- Remaining hurdles
The grid operator can limit the feed-in