IT-Permit: grid connection
When planning a PV installation, it is important to identify the nearest connection point to the grid. Check if there are any limitations on feed-in power. Review the hardware requirements for connecting your PV system to the grid.
Support to request an approval from power grid operator for your PV plant. The fee for obtaining the estimate varies based on the system's power capacity.
- Offered by
- E-distribuzione
- What the initiator needs to provide
Sign up on the e-distribuzione website; Enter the location, general system data, and the required attachments, including the cadastral map, electrical diagram, and the fee.
- Result
After submitting the connection request, you will receive the corresponding quote. The timeframes prescribed by ARERA are: 20 working days for power up to 100 kW; 45 working days for up to 1,000 kW; 60 working days for over 1,000 kW.
- Remaining hurdles
The grid operator can limit the feed-in