English Deutsch

For systems up to 250 kW, the feed-in capacity can be temporarily or generally reduced to an agreed maximum value to guarantee safe and efficient operation of the grid. The limitation may not exceed 1% of the maximum capacity at the grid connection point.

Find how much feed-in the grid can handle. If the grid infrastructure is limited, your feed-in power may be restricted.

Offerto da
Energy Netze Steiermark
Cosa deve fornire il promotore

Smart meter's ID (aka Measurement Point)

Risultato

Max available feed in power

Ostacoli residui

Some regions only allow a small feed in power