88 servizi

AT: Analysis - Structural

If a structural analysis is required, then it must include the following: For a new building: Proof of the load-bearing capacity, usability, and durability of the load-bearing structure in accordance with OIB-RL 1. For the subsequent installation of a PV system: Survey of the existing structure, at least to Level 1, in accordance with the guidelines of OIB-RL 1; Proof of the minimal impact of the measure (load increase <= 3%) OR Proof of the load-bearing capacity, usability, and durability of…

Austria Pianificazione

AT: Permit - Building Code

Some PV installations need building notification (Bausanzeige), some need building permit (Baubewilligung) some need none. In any case, compliance with fire protection, glare, and structural integrity is required.

Austria Pianificazione

AT: Analysis - Max Feed-In Steiermark

For systems up to 250 kW, the feed-in capacity can be temporarily or generally reduced to an agreed maximum value to guarantee safe and efficient operation of the grid. The limitation may not exceed 1% of the maximum capacity at the grid connection point.

Austria Pianificazione

AT: Analysis - Free capacity per substation

Understand if the substation still has free capacity. Available or booked capacities per substation (network level 4) are published quarterly.

Austria Pianificazione

AT: Permit - Grid Connection

Grid operators cannot deny Systems <= 20 kW from being connected to the grid. A feed-in capacity is guaranteed up to the extent of the already agreed consumption capacity.

Austria Pianificazione

AT: Analysis - Grid Connection Costs

Pay grid provision fee (Netzbereitstellung) and the grid access fee (Netzzutrittsentgelt). The distribution system operator has 2 weeks (network level 7) or 1 month (network levels 1 to 6) from the receipt of a request to provide a cost estimate.

Austria Pianificazione

AT: Analysis - Consumption

Determine the annual consumption. Your annual electricity demand is stated on your utility bill. You also find it on the web portal of your electricity provider and/or grid operator.

Austria Pianificazione

AT: Analysis Consumption Profile

Electricity consumption can be estimated based on old electricity bills. Alternatively, smart meters can be read via the service portal of the grid operator. These time series provide insight into the dynamics of electricity consumption.

Austria Pianificazione

AT: Analysis - Feed-in tariffs

Compare various prices for excess solar electricity, summarized on pvaustria.at

Austria Pianificazione

AT: Analysis - Solar Radiation and Electricity yield

1) Determine the Annual Solar Radiation for your address (in kWh/m2/a). 2) Multiply with your plant size (in m2) and efficiency (kWelectric / kWradiation)

Austria Pianificazione

AT: Analysis Economical

Use the calculation tool

Austria Pianificazione

AT: Analysis - Tax

Anyone who operates a photovoltaic system must consider Austrian tax law. The revenue from electricity sales and/or the use of self-generated electricity for private purposes creates an income tax obligation. Additionally, the question of VAT liability must be clarified.

Austria Pianificazione

BG 01: Community building

Create an initiative committee by experienced individuals. Organize a steering committee with a project coordinator. Engage local individuals interested in PV and CEPs. Introduce and promote the CEP to local authorities.

Bulgaria Pianificazione

BG 02: Community assessment

Evaluate the purpose of the E.C. and its size to measure its potential impact. Identify the members of the community to understand its composition. Potential future members have to be considered as well.

Bulgaria Pianificazione

BG 03: CEP Purpose and Vision Proposition

Definition of the purpose and vision of the CEP, including the outcomes, the overall benefit, and how the members will benefit from it. This very initial step makes sure that all participants share the same values and are on one page regarding the project concept.

Bulgaria Pianificazione

BG 04: Environmental feasibility check

Check with normative base and local environmental institution (RIEW) whether the implementation of roof-top and stand-alone PV installation up to a certain plant size require an environmental impact assessment. The environmental assessment is necessary if your plant size exceeds 30 MW or if PV plant is freestanding object.

Bulgaria Pianificazione

BG 06: Documentation and Approval - Technical projects

Prepare technical documentation for the PV plant/EC to apply for different permits, including: building permit, grid connection permit, etc.

Bulgaria Pianificazione

BG 07: Analysis - Load bearing capacity for installation of PV systems

Determine whether the roof structure can bear additional load of PV installation and how big the load can be.

Bulgaria Pianificazione

BG 05: Preliminary building permit for PV plants and direct power lines in urban environments

Obtain authorization by local authorities in order to construct PV plant and direct power lines.

Bulgaria Pianificazione

BG 08-1: Analysis - Connection to the power grid for self consumption

Identify the nearest connection point to the grid with the DSO and check whether there are possibilities for augmentation of the feed in power. Check if there are any limitations on feed-in power, as well as the hardware requirements for connecting the PV system to the grid.

Bulgaria Pianificazione

BG 08-2: Analysis - Power distribution cabinets

Assessment whether the existing power cabinets that service the building are sufficient to handle the current of the PV plant. Determine the ownership of power cabinets.

Bulgaria Pianificazione

BG 09-2: Analysis - Free capacity of the feeder/low voltage grid connection line

Obtain information of the DSO free grid capacity to assess whether it will be possible to sell surplus energy to the electricity market.

Bulgaria Pianificazione

BG 09-1: Analysis - Additional grid connections

For a CEP/EC with several buildings included and several direct power lines between the participants more than one grid connections with different characteristics maybe explored.

Bulgaria Pianificazione

BG 09-3: Obtaining a Permit for connection to the grid

To build a PV plant first of all is necessary to obtain preliminary permit by the DSO, stating that connection to the grid in the area is possible and is generally available.

Bulgaria Pianificazione