Check with normative base and local environmental institution (RIEW) whether the implementation of roof-top and stand-alone PV installation up to a certain plant size require an environmental impact assessment. The environmental assessment is necessary if your plant size exceeds 30 MW or if PV plant is freestanding object.

Study the normative prerequisites for environmental permits based on your specific technical project concepts.

Offerto da
Municipality of Dryanovo
Cosa deve fornire il promotore

Environmental normative base; Basic technical project concept of EC

Risultato

Clear understanding of environmental permitting procedure for the EC projects

Ostacoli residui

The environmental regulations in Bulgaria are very dynamic and thus a change in the required permitting process cannot be ruled out