Identify the nearest connection point to the grid with the DSO and check whether there are possibilities for augmentation of the feed in power. Check if there are any limitations on feed-in power, as well as the hardware requirements for connecting the PV system to the grid.

Explore with DSO the available on-site options for connecting the PV plant, energy storage and direct power lines for self consumption by CEP/EC participants.

Offerto da
Electricity System Operator Bulgaria (ESO)
Cosa deve fornire il promotore

Application for connection to the grid. Wiring schemes and drawings of existing building.

Risultato

Wiring schemes (internal and external) for all buildings and direct power lines within the scope of the CEP/EC approved by the DSO.

Ostacoli residui

Not enough connection capacity to the grid infrastructure.