Catalogo dei servizi
88 servizi
HR-14-Analysis - Economics
When evaluating a PV system, determine how much of the generated electricity you can use personally versus how much can be sold or donated to others.
HR-15-Preassessment - Financing
The feasibility of a PV installation is very much dependent on the possibility to finance the endeavor.
HR-16-Analysis - PV System - Documentation and Approval - Main Project
Generate a description or a graphic presentation or a conceptual design. Document shall include: a map of the electrical design, a map of the construction project, the structural analysis of the roof, architectural design.
FR-01-Forming a pilot group
Launching a photovoltaic community energy project is complex and requires good information at the very start. It is better to form a small team of motivated people. The website photovoltaique.info is the reference source of information.
FR-03-Getting approval to launch the project
To launch a photovoltaic community energy project within a condominium, you are advised to get approval by other people in your community, such as the council board of your condominium or the General Assembly.
FR-04-Defining your value proposition
Once your building potential for photovoltaics has been studied, you have to choose how you wish to value your electricity, and you have to plan the works to make your roof PV-ready. Several models of energy may take place in Paris.
FR-09-Getting permit - Urbanism and heritage protection
A permit is needed from the local authority, Paris City administration, according to urbanism and heritage protection rules. Your PV plant will be located on rooftops in most cases and may cause changes in the aspect of your building.
FR-09-Getting permit - Focus on heritage protection
PV plant in Paris will be located on rooftops in most cases. Such PV plant changes the aspect of a building. It has to be authorized according to urbanism and heritage protection rules.
FR-04-Studying the feasibility of the project - PV-ready building
Implementing a PV plant on your roof requires your building to be PV-ready in terms of: load bearing capacity; water-proofing; human accessibility; accessibility for PV panels; among other aspects.
FR-02-Analysing opportunity 4-Wiring
The goal of this step is to anticipate possible works of adaptation of your building wiring infrastructure to a future PV plant. The wiring infrastructure in your building connects the public grid to each of the private apartment and each of the collective equipments.
FR-10-Requiring connection to the grid
Connection to the grid is required for any PV plant. You have to go through a standard procedure with your DSO, Enedis in Paris.
FR-10-Simulating connection to the grid
Connecting to the grid is a key step. It is important to simulate and anticipate before you actually demand connection. You have to pay attention to assessing the need for renovation of your building electric wiring and meters.
FR-10-Getting a Proposition for grid connection
Once you have completed your demand for grid connection (DCR), you will receive within a defined timeframe a Proposition with a price to pay for connecting to the grid (PTF or PDR) that you will have to accept to launch construction work.
FR-02-Analysing opportunity - PV project within a holistic approach
Planning works on your roof for the implementation of a PV plant is an opportunity to consider the building as a whole. You are advised to investigate the need for works in all technical dimensions, structural, architectural and environmental.
FR-02-Analysing opportunity 2-Consumption
Once you have estimated your potential for production, you have to question which use you will make of the electricity generated. Knowing your building or community consumption will give you an insight into the share of electricity generated that may be consumed.
FR-02-Getting consumption data
In order to analyse precisely the potential for self-consumption, it is useful to get first the actual consumption data of the buildings within the community. Enedis provides a free service called dataconsoelec.
FR-12-Contracting purchase contract
You can contract a purchase contract if you choose to sell part or totality of your electricity. Either you sell it within a collective self-consumption operation (CSC) or to an independent buyer (PPA), or to an obliged buyer for 20 years.
FR-02-Analysing opportunity 1-Production
Estimating the production available on your building roof is probably the first step. It depends on many factors such as the surface of the roof available for PV panels, the energy it receives from the sun, its inclination and orientation.
FR-04-Studying the feasibility of the project
Once your project is launched and approved, it is necessary to have Professionals study the feasibility of your project. Feasibility study will give you a more precise simulation of production potential.
FR-02-Analysing opportunity 3-Economics
Once you have estimated potential for production and self-consumption of electricity, you have to know how much it should cost and how much you should benefit from it. The preassessment of economic balance gives you an estimation of the return on investment.
IT-Manifestazione di interesse ad aderire a una CER
Informare la cittadinanza della costituzione della CER nel Comune pubblicando l'avviso di manifestazione di interesse e raccogliendo le adesioni.
IT-Individuazione dei promotori della CER
Riunire persone, PMI ed enti locali motivati che vogliono partecipare a una CER.
IT-Individuazione delle CER esistenti
Aderire a una CER già costituita può semplificare notevolmente il percorso rispetto alla creazione di una nuova. Le comunità esistenti hanno di solito già completato i principali passaggi amministrativi, legali e tecnici necessari per operare.
IT-Valutazione della comunità
Per avviare una propria CER è importante partire da un'idea di progetto, individuando un primo gruppo di promotori, il perimetro operativo della CER, le fonti rinnovabili da utilizzare e il profilo generale di consumo/produzione.