166 services

AT: Analysis - Structural

If a structural analysis is required, then it must include the following: For a new building: Proof of the load-bearing capacity, usability, and durability of the load-bearing structure in accordance with OIB-RL 1. For the subsequent installation of a PV system: Survey of the existing structure, at least to Level 1, in accordance with the guidelines of OIB-RL 1; Proof of the minimal impact of the measure (load increase <= 3%) OR Proof of the load-bearing capacity, usability, and durability of…

Austria Planning

AT: Permit - Building Code

Some PV installations need building notification (Bausanzeige), some need building permit (Baubewilligung) some need none. In any case, compliance with fire protection, glare, and structural integrity is required.

Austria Planning

AT: Analysis - Max Feed-In Steiermark

For systems up to 250 kW, the feed-in capacity can be temporarily or generally reduced to an agreed maximum value to guarantee safe and efficient operation of the grid. The limitation may not exceed 1% of the maximum capacity at the grid connection point.

Austria Planning

AT: Analysis - Free capacity per substation

Understand if the substation still has free capacity. Available or booked capacities per substation (network level 4) are published quarterly.

Austria Planning

AT: Permit - Grid Connection

Grid operators cannot deny Systems <= 20 kW from being connected to the grid. A feed-in capacity is guaranteed up to the extent of the already agreed consumption capacity.

Austria Planning

AT: Analysis - Grid Connection Costs

Pay grid provision fee (Netzbereitstellung) and the grid access fee (Netzzutrittsentgelt). The distribution system operator has 2 weeks (network level 7) or 1 month (network levels 1 to 6) from the receipt of a request to provide a cost estimate.

Austria Planning

AT: Analysis - Consumption

Determine the annual consumption. Your annual electricity demand is stated on your utility bill. You also find it on the web portal of your electricity provider and/or grid operator.

Austria Planning

AT: Analysis Consumption Profile

Electricity consumption can be estimated based on old electricity bills. Alternatively, smart meters can be read via the service portal of the grid operator. These time series provide insight into the dynamics of electricity consumption.

Austria Planning

AT: Analysis - Feed-in tariffs

Compare various prices for excess solar electricity, summarized on pvaustria.at

Austria Planning

AT: Analysis - Solar Radiation and Electricity yield

1) Determine the Annual Solar Radiation for your address (in kWh/m2/a). 2) Multiply with your plant size (in m2) and efficiency (kWelectric / kWradiation)

Austria Planning

AT: Analysis Economical

Use the calculation tool

Austria Planning

AT: Analysis - Tax

Anyone who operates a photovoltaic system must consider Austrian tax law. The revenue from electricity sales and/or the use of self-generated electricity for private purposes creates an income tax obligation. Additionally, the question of VAT liability must be clarified.

Austria Planning

AT: Insurance

Find insurance. Covers damage from hail, storms, lightning strikes, and fire. Many building insurances already include coverage. Consider separate insurance for off roof installations. Typical costs: 2 EUR per kWp

Austria Realisation

AT: Financing - Crowd Financing

Apply for a crowd financing scheme with GeReGi.

Austria Realisation

AT: Financing - Grant

The EAG grants investment subsidies, for which project proposals must be submitted to ongoing funding programs. The amount of the investment subsidy is limited to a maximum of 30% of the investment volume directly required for the construction of the system.

Austria Realisation

AT: Enquire binding offer for plant construction

Provide pre-planning documents, scope of equipment, information about location, address, restrictions, information about building, roof, electrical installations and related locations including pictures, provide grid access confirmation document.

Austria Realisation

AT: Metering Device

Request installation of a meter. The installation of a meter must take place within 3 working days (standard load profile) or 8 working days (load profile meter) after the completion of the registration.

Austria Realisation

AT: Norms and Standards

Ensure that the system complies with the norms and standards

Austria Realisation

AT: Legal Entity

An energy community needs to become a legal entity. The cheapest option is to establish a society (Verein) at the local authority: District Commission (Bezirkshauptmannschaft) or Regional Police Directorate (Landespolizeidirektion)

Austria Realisation

AT: Registration - Market Participant

ebUtilities.at provides the market partner directory which includes registered market partners. Operators of (future) energy communities need to register on the platform. They will receive a unique Market Partner ID after approximately 2 days.

Austria Realisation

AT: Registration - Grid Operator

Energy communities need to sign a contract with the grid operator.

Austria Realisation

AT: Registration - EDA Portal

The EDA Portal is a web platform for energy service providers and energy communities. It provides easy access to energy industry data.

Austria Realisation

AT: Registration - EC members

With your eda access, you can create a new energy community in your eda portal. Afterwards you can invite others to join your community.

Austria Realisation

AT: Registration - Tax

You will receive mail from the tax authority. Notify them about the commencement of association activities and provide a signature sample.

Austria Realisation